Coca-Cola factory

Chief designer:

State Enterprise of the Ministry of Defence of Ukraine “Central Design Institute”
Customer:
The Coca-Cola Company

The design was carried out in cooperation with 39 Ukrainian and 24 foreign design organisations. The total area is 24.5 hectares. The planned enterprise will produce Coca-Cola, Fanta and Sprite soft drinks with a total capacity of 3,500,000 litres per day. Запроектовані слідуючі споруди:

  • production building with a total area of 47,952 m2;
  • administrative and residential, 4-storey building with a total area of 984 m2;
  • engineering networks and structures;
  • three truck parking areas with 150 spaces;
  • 1.25 km long access road.

The factory complex will provide approximately 770 jobs.